Part F and MVHR commissioning explained
Last updated 23 November 2026
This is not legal advice. Check with your building control body.
England
Mechanical ventilation in a home must be commissioned. For a new home, the airflow rates must be tested and the results given to building control within five days of the final test (Building Regulations 2010, regulation 42). Installers registered with a ventilation competent person scheme (BESCA, Blue Flame Certification, Certsure/NICEIC or NAPIT) can self-certify the work.
Checked 23 November 2026
Wales
Wales has its own Approved Document F. Mechanical ventilation must be commissioned, and installers registered with a ventilation competent person scheme (BESCA, Blue Flame Certification, Certsure/NICEIC, NAPIT or Stroma) can self-certify the work. A new Approved Document F Volume 1 for Wales takes effect on 4 March 2027.
Checked 23 November 2026
Scotland
Scotland doesn't use the England and Wales competent person schemes for ventilation. Building standard 3.14 requires mechanical ventilation systems to be commissioned to show they work, and written operating and maintenance information to be provided. We haven't found an official Scottish requirement for a named installer qualification, so ask your local authority building standards team what they'll expect.
Checked 23 November 2026
Northern Ireland
Fixed mechanical ventilation must be tested and commissioned. The person doing the work must send the district council the airflow test results within five days of commissioning, and give the owner information on running and maintaining the system (Building Regulations (Northern Ireland) 2012, regulations 65 to 68).
Checked 23 November 2026
The commissioning record
Many installers use the BEAMA Part F ventilation commissioning sheet (checked 23 November 2026). Whatever form is used, you should end up with measured airflows for each room and the settings the unit was left on. Keep it – a servicing engineer will need it.
Qualifications to ask about
Ask for the individual fitter's certificate. See BPEC's domestic ventilation systems qualification (checked 23 November 2026). There is no public BPEC register to check it against.
Questions
- Does Part F require MVHR?
- In England, Part F does not require MVHR in every new home; other ventilation approaches are recognised. Wales has its own Part F. Scotland uses building standard 3.14 and Northern Ireland uses Part K. Check with your building control body.
- What is an MVHR commissioning record?
- In England, new-home airflow test results must be given to building control within five days of the final test. Wales requires commissioning under its own Part F. Scotland requires commissioning under standard 3.14. In Northern Ireland, airflow results go to the district council within five days of commissioning. Keep the measured airflow record.
Sources
- Approved Document F (gov.uk) (checked 23 November 2026)
- Regulation 42 (checked 23 November 2026)
- Competent person schemes (gov.uk) (checked 23 November 2026)
- Approved Document F (gov.wales) (checked 23 November 2026)
- Competent person schemes (gov.wales) (checked 23 November 2026)
- Domestic Technical Handbook, April 2026 (gov.scot) (checked 23 November 2026)
- Building standards (gov.scot) (checked 23 November 2026)
- Part K of the regulations (checked 23 November 2026)
- Technical Booklet K (Department of Finance) (checked 23 November 2026)
- BEAMA Part F ventilation commissioning sheet (checked 23 November 2026)
- BPEC domestic ventilation systems qualification (checked 23 November 2026)